Technical safety and work environment analyses at Aker BPs Alvheim

Kaefer Energy (KE) had the mission of doing modification work in context with a new kitchen/galley at Aker BPs Alvheim. The solution was made in cooporation between Aker BP and Norema. Petrell had a central role regarding technical safety and work environment during the study and implementation phase of the galley in Des 18/Jan 19. The aim was to make sure that the solution satisfied the requirements of NORSOK S-001 and S-002. Petrell did

  • Develop HSE and work environment program (with focus on installation)
  • Execute workshop regarding analyzing the work environment
  • Give input when the WEAC was updated
  • Participate on the design evaluation
  • Leade HAZID for the installation work
  • Mark-up of plot plans
  • IDC
  • General project support regarding technical safety and work environment
  • Participate on project meetings
  • Status reporting
  • Give inputs on the design report